|
Wednesday, July 30, 2003
Tuesday, July 29, 2003
Friday, July 25, 2003
Thursday, July 24, 2003
Tuesday, July 22, 2003
Monday, July 21, 2003
-
Engineering's done, plans are complete and
an re-inspection is scheduled for tomorrow. Keep those fingers
crossed.
-
Laurel and I went looking at tile over the
weekend.

Thursday, July 17, 2003
-
We've run into a small snag during the shear wall analysis process. The set of plans
that was used for the analysis did not contain a current
configuration of the kitchen exterior wall. Doing a little
rework on the analysis and then the plans go back to Yurkovic
Design.
-
Applied to the
city for the water meter tap.
-
"Temporary" website is almost
pau (finished). Finally!!! Seems nothing moves quickly on this
project.

Wednesday, July 9, 2003
Tuesday, July 8, 2003
Monday, July 7, 2003
Wednesday, July 2, 2003
Tuesday, July 1, 2003
Monday, June 30, 2003
Friday, June 27, 2003
Thursday, June 26, 2003
Wednesday, June 25, 2003
Tuesday, June 24, 2003
Monday, June 23, 2003
Sunday, June 22, 2003
-
House footings were finally
dug on Thursday. The other retaining walls, which were suppose to be
done at that same time, seem to have gotten missed.
-
The blue diamond-shape in
the upper-right quadrant of the live picture is the handy work of a few
local miscreants who decided to dump the porta-potty down the hill.

Wednesday, June 18, 2003
Wednesday, June 11, 2003
-
House is placed on the lot
and the footings are outlined. Still need to locate and mark the
retaining wall footings for the north side. This wall holds up the
entrance-way.
-
The driveway retaining wall
was shot 8" low, but we'll fix that up with a minor do-over.

Monday, June 9, 2003
Thursday, June 5, 2003
Wednesday, June 4, 2003
-
The lot's almost back to the
original grade level. Today, the trucks just kept coming and coming and
coming. At 10 to 12 cubic yards per load, it takes a while to haul in
800 cubes of dirt. This "dirt" phase, which began in early March, should
be wrapped up Thursday. Nothing is easy.

Tuesday, June 3, 2003
Wednesday, May 21,
2003
-
Waiting for dirt...

Thursday, May 15,
2003
-
Retaining wall is being
waterproofed today. Backfilling is scheduled to start on May 20th. We'll
be trucking in 800 cubic yards of dirt from Boss Kean's ditch.
Boss Paul: "That ditch is Boss Kean's ditch. And I told
him that dirt in it's your dirt. What's your dirt doin' in his ditch?"
Luke: "I don't know, Boss."
Boss Paul: "You better get in there and get it out, boy."

Aloha Friday, May 9,
2003
Thursday, May 8, 2003
Wednesday, May 7, 2003
Tuesday, May 6, 2003
Friday, May 2, 2003
Thursday, May 1, 2003
Wednesday, April 30,
2003
-
Most of the driveway retaining
wall blocks were set.
See the
pictures...
-
After this, the rebar in the
wall to be inspected. When that's green-tagged, the wall gets grouted
(filled with cement) and then it has to cure for 7 days.

Monday, April 28,
2003
Thursday, April 24,
2003
-
After a little intervention
with the city, the retaining wall is
green-tagged. Cement trucks should be on the
way (if you believe that, you'll believe Sam the Dog knew how to knit).

-
Some people would say we're not making
progress,
but look...

Wednesday, April 23,
2003
-
We're at the third chomp at
the apple--still red-tagged. First we needed
the retaining wall permit, next it was engineering on the specifications
for the wall. Now the inspector wants a drawing of what the wall will look
like. Since the construction workers were able to figure out how to build
it from the specs, doesn't it seem a bit strange that we'd need a drawing
just to approve the work?
-
Rubble removed.

Tuesday, April 22,
2003
Monday, April 21,
2003
Aloha Friday, April 18,
2003
-
Another week has passed and
we've made very little, if any progress. DSD issued the permit for the
wall on Monday. Inspection was called in for Wed. Again, he never showed.
Inspector did finally show on Thursday and red-tagged it again. This time
it was for engineering on the retaining wall. The specs for this wall are
contained in the blueprints that were approved by the city. These specs
are in table form and are basically engineering boilerplate. Inspector
seems to think we need an engineering stamp. This is getting ridiculous!

Aloha Friday, April 11,
2003
Thursday, April 10,
2003
Wednesday, April 9, 2003
Tuesday, April 8, 2003
-
The footing trenches for the retaining wall
were refined and extended to include lot line wall footings. This required
removing all the remaining (visible) Oleander roots.
-
Re-bar for the drive retaining wall was
delivered today.

Saturday, April 5, 2003
Friday, April 4, 2003
Thursday, April 3, 2003
Wednesday, April 2, 2003
Tuesday, April 1,
2003
Monday, March 10 to Saturday, March 29
-
The Great Dirt
compaction effort.
Work was done in three major sections, starting from the north end, by
digging the loose dirt out until native soil was encountered, then putting the
loose soil back, spraying with water then driving over it multiple times with
the track hoe or front loader. It was a three week effort to get it compacted
to the height for the driveway retaining wall construction. Once the retaining
wall is built, the pad level will still need to be raised approx. 7 feet on
the South end (where the retaining wall goes) and 4 feet on the North end.
March 26th Pictures...

Saturday, March 8, 2003
-
Following an engineering
review, it has been determined that soil is going to need to be
removed down to native strata, debris removed, and soil replaced and
re-compacted. Bummer!!!

Tuesday, March 4, 2003
-
Moving the debris today.

Monday, March 3, 2003
Friday, February 28, 2003
Thursday,
February 27, 2003
Wednesday, February 26, 2003
Tuesday, February 25, 2003
Monday, February 24, 2003
-
Activity
at last!!! Most of the oleander bushes were removed (they were huge).
Their carcasses lay in the upper-left part of the picture. Now
comes the fun part--removing the root structure.
Pictures...
-
Construction Cam
is finally up in production mode. Up next -
moving dirt for the south driveway retaining wall.

Prior Journals |