|
Wednesday, December 31, 2003
-
No work today. Pre-New Year Holiday I
guess.
-
Yesterday we found 2 stainless steel sinks
with drain boards/counter tops at a used restaurant equipment
place. The two units we found are absolutely perfect for the
greenhouse (high humidity area) and the roof deck (severe sun
exposure). I ordered them this morning and they've been
delivered about 2:00 P.M. With new faucets and a little elbow
grease and Barkeepers Helper they'll look wonderful.
-
Happy New Year!!!

Monday, December 29, 2003
Saturday, December 27, 2003
-
Because of the long holiday weekend, there
was no work done on Friday.
-
Tried doing framing cocktails on Friday,
but it was colder than snot. Burrrr!
-
I'm working on do lists and project plans
to help insure that everyone's on the same page and to try and
expedite the completion of this puppy.

Wednesday, December 24, 2003
-
The block work for the front retaining
wall is completed and green tagged and ready for grouting.
Pictures
-
Other than the wall work, not much has
happened this week. The plumber was up today to do a little
more drain pipe work. Seems like every place he needs a hole,
there's a glulam beam in the way.
-
Enjoy the Holidays!!!

Thursday, December 18, 2003
-
The plumber started installing the drain
pipes on the first level and adding the extensions to the 2nd
floor.
-
The footing for the front retaining wall
was poured.
-
Still trying to get the damn deck tile
situation squared away. Arrrrgh!!!

Wednesday, December 17, 2003
-
The framers are in doing a little
touch-up. They've correct the columns in the shower. We're
still short soffits in the kitchenette and over the laundry
counter.
-
The front retaining wall steel got green
tagged.
-
Still no sign of the plumber.

Monday, December 15, 2003
-
Sometime last Friday, the rebar gnomes
showed up and added steel to the footing for the front
retaining wall.
-
On Sunday, Randy started to install a
little PVC pipe to bring water to pots we may want to put on
the upper lanai. Needed a couple of extra tools so the project
didn't get too far. We'll try again on Tuesday.
-
Spent another Hour and a half picking out
plumbing fixtures. We're getting close.

Aloha Friday, December 12, 2003
-
We spent 3 very long hours yesterday
picking out plumbing fixtures and we're still not
done--getting close, though.
-
As you can see from the interior camera,
we had a little rain last night.
-
Turns out the bridge is going to be quite
a bit longer than shown on the plans, so we're adding a center
support column. I love "design on the fly."

Thursday, December 11, 2003
-
Rumor is that the nail/shear inspection
passed, but the City's permit website says "Carry Over." I'm
not sure what that means.
-
Had an on-site meeting to discuss the
shower enclosure and lanai railings. The shower enclosure will
be suspended over the rock mosaic tile. We're looking at glass
"railings" on the upper lanai. This should provide a very cool
look and it won't obstruct the view.
-
Started excavating the footings for the
front retaining wall and bridge. To reduce the required truss
size, we've decided to add a center support column to the
bridge.
-
The two columns in the master shower that
support the shower heads were built 9" wide and 12" deep.
Should have been the other way around. Fix in the works.
-
Framers are wrapping up the structural
blocking of the roof deck.
-
Off to meet with the plumbing fixture
supplier this afternoon. I have a feeling this is going to be
an expensive trip.

Tuesday, December 9, 2003
-
The HVAC crew wrapped up the duct work on
Monday afternoon. The bar soffit seems to have become "vent
central" with openings blowing north, west and two south.
-
Word has it that the framing inspection is
scheduled for Wednesday. Cross your fingers.
-
As part of the new camera installation, I
had to 'tilt' the pole on exterior camera and redo a little
wiring. While the camera was accessible, Laurel used paper
towels and spit to clean the Plexiglas screen and now the
picture is MUCH better. The pole camera survived a rather
brutal summer.

Sunday, December 7, 2003
-
The HVAC crew worked on Saturday
installing duct work on the main level. Looks like they're
about 30% done with the ducts.
-
Live camera #2 was installed today. It'll
be a traveler. Still have a couple of little tech issues to
work out, so don't be bothered by an occasional picture with
little dots at the bottom.
-
Picked out the tile for the roof deck,
stairs (rear) and 2nd floor lanai on Saturday. We also went
and look at more granite samples.
-
The tie down brackets, straps and bolts
are huge. I don't think we have to worry about this baby
blowing away.

Aloha Friday, December 5, 2003
-
The HVAC crew is installing the duct work,
vent fans, dryer vent and coolant lines on the lower level.
They were able to get all of the duct work in the trusses on
this level, so we won't have to lower the hall ceiling.
-
The framers are installing tie down straps
and they added sheeting to the south and east walls of the
dining room. We've got little busy bees all over the place.
-
2nd camera's up in local test mode.
-
I woke up at 3:00 this morning, thinking
about all the house-related stuff we have to do. Couldn't
sleep, so I designed light fixtures--they also cover a flaw in
the slab--for the lower level hall.

Thursday, December 4, 2003
-
Met with Mary at S. M. Services again and
tried to make some decisions on counter tops, wood flooring,
tile and carpet.
-
Testing the new hardware needed to add a
live camera to the Hale Nani interior.
-
I've said it before and I'll say it again,
trying to build a contemporary house in Arizona is like trying
to build sand castles in the Arctic.

Tuesday, December 2, 2003
-
Met with a cabinet vendor on-site
today. Estimate should be available in a couple of days.
-
No work on the framing today. It
looks like the guys are addressing a few issues with the sheer
walls and tie downs. They sheeted the north wall of the
office.
-
We're at revision 3 of the main level
lanai box beam, but it's still not right. Ladder bracing is
gone, but it's smaller than the width is smaller than
the 18" column on the south end.
-
Last night, Laurel and I attended a
presentation at Cooking with Class that was put on by Dacor,
one of our potential appliance brands. It was interesting,
informative and included a great dinner prepared in Dacor
appliances!

Saturday, November 29, 2003
-
Got another cabinet estimate today; this
one from your basic "Big Box" DIY store. Made the first
estimate not look that bad. It's still not close to our
allowance, though. Got us wondering where the allowance number
came from.
-
Going back to review the appliance
selections.

Aloha Friday, November 28, 2003
-
Much to my surprise, the metal duct work
was delivered today.
-
No framing work today (long Thanksgiving
holiday
-
Barb, Herb, Rick, and Chris joined us for
cocktails and hotdogs on "the frame."
-
We've been trying to get the box beam on
the upper lanai framed so that it'll enclose the sunshades.
Getting closer, but it still needs a little work.
-
The soffit over the bar looks great!

Tuesday, November 25, 2003
-
Met with the sunscreen vendor on-site.
We're having shades installed between the columns on the west
side of the upper lanai and on the two northwest-facing
windows. They'll be automatically operated by sun sensors and
there's also a sensor to retract the shades if the winds kick
up--they're basically 11'x8' sails.
-
Climbed the ladder and made the first
visit to the almost complete roof deck. WOW!!! The view is
fantastic.
-
Discussed a problem with how the gables
and the greenhouse main structure interface with the house.
Someplace along the way, I think the ball got dropped here.
This has to get fixed.
-
Worked with the framers to make sure the
wet bar and the soffit above it got properly dimensioned.

Monday, November 24, 2003
-
Had to change the size of a couple of
doors today. The 9' wide by 8' high doors (9080) in the dining
room are too big to just have two segments. We're reducing the
dining room door to a split 8080. The door in the media room
is being changed to a 3-part 9080.
-
Got the design for the box beams on the
top of the lanai squared away.
-
We putting sheeting over the great room
and working on framing the top section of the stair tower.
-
Spent Sunday playing with flooring
samples.

Saturday, November 22, 2003
-
On Friday night and this morning we began
the granite/tile selection process. I think we made an amazing
amount of progress in that we have finalists for the lower
level baths and kitchenette, the kitchen and the bar--almost
all within the our allowances. We schlepped home tons of
additional samples, too.
-
Framer noticed a big discrepancy between
the plans he was working off of and the tie-down bolts in the
footings. This all goes back to some early problems with
some shear wall analysis and a little re-engineering. I'm sure
Mike and Herb will get it sorted out.
-
Had another marvelous sunset cocktail hour
on the upper lanai.

Thursday, November 20, 2003
Wednesday, November 19, 2003
-
Changed our minds (imagine that) and
switched the black windows to mill finish (aluminum). It
should go nicely with the greenhouse structure and should look
good with the dark house exterior.
-
Met with the HVAC contractor and made a
ton of decisions. They include:
-- Switched from gas furnaces and water heater to a heat pump
and electric water heater. This was done because of problems
venting the systems and the requirements for combustion air
vents in the equipment room. I just doesn't work in an air
conditioned space
-- Moved the second air handler to the roof over the kitchen.
This simplifies the chases and duct work requirements and
should be hidden from view by the parapets
-- Specified evaporative cooler vent locations for the lanai
-- Lowered the pantry ceiling to 9'-0" to accommodate duct
work
-- Dropped the equipment room ceiling to 8'0" to accommodate
lower level return air duct
-- Lowered the kitchen closet ceiling to accommodate the duct
work for the greenhouse evaporative cooler.
-
Great room and dining room ceiling details
are being framed.
-
Soffit over the garage door is complete.
It looks great.
-
Herb decided he didn't like the look of
the roof over the Juliet balcony in the master bedroom (it
slopes slightly), so he's redoing it.
-
Greenhouse knee wall is pau (done).
-
Mike got the rest of the details for
framing in the dumb waiter shaft.
Tuesday, November 18, 2003
-
Met with the window contractor to select
sliding doors and all windows. After much deliberation, we've
decided to with a black finish.
-
Master bedroom wall units have been
framed.
-
Making progress on framing and beam
structure for the staircase from the top of the main stairs
(interior) to the roof deck (exterior). Herb came up with some
fantastic solutions to some tough problems.
-
Waiting for back-ordered 1-1/8" plywood to
finish the great room roof sheeting.
-
Told Mike to plan on little architectural
jig-jogs in the lower level hall to cover up a little plumbing
placement problem.
-
Added soffits to the downstairs
kitchenette and deleted them from the kitchen.

Saturday, November 15, 2003
Thursday, November 13, 2003
-
Raising the master bath floor and doing
other framing details.
-
Spoke with two cabinet companies. I think
we're getting closer.
-
Laurel and I spent a very stressful, but
productive evening picking out appliances. That kitchen's
going to be way cool.
-
Friday night slab-tales have been renamed
"frame-tales."

Wednesday, November 12, 2003
-
Rain day. Not much going on.
-
Met with Mike (General Contractor), Herb
(Framing Contractor) and Nathan (Stair Contractor) to discuss
stair design and resolve a problem with a beam over that
supports the stair to roof deck transition.
-
The columns on the upper lanai are
finished. They really have very little impact on the view.
-
Most of the roof sheeting, except for the
Great Room, is in place.
-
Tomorrow, Laurel and I are going to talk
with two more cabinet builders.

Tuesday, November 11, 2003
Thursday, November 6, 2003
-
Herb's crew raised the lanai today (out of
camera range) and I missed it (dang!). It went up without a
hitch.
-
Roof trusses were delivered on Wednesday.
They should be installed on Friday.
-
Fixed the MBR window heights, and did some
other framing detail work.

Monday, November 3, 2003
-
Roof trusses and the new glulam beam that
supports the great room trussing should be delivered on
Wednesday. I doubt we'll see any work before then.
-
I'm starting the design process for camera
coverage on the inside of the structure.

Spooky Aloha Friday, October 31, 2003
-
The past few days have been, at once, some
of the most exhausting, exhilarating, frightening, perplexing,
frustrating and delightful times I can remember. After years
of planning, watching this baby come together in three
dimensions is truly exciting, but there's always a little second
guessing going on and hoping we've made the right decisions.
Anyway, it's looking marvelous!
-
Had another on-site meeting today with
Mike and Herb to work out details for raising the master bath
floor. We're also making a 'major' change to the wall behind
the bar. We're opening it up from to expose the views from the
kitchen and dining rooms. This is a great change. Don't know
why we didn't see it sooner. It involves a new glulam beam and
hanging the great room trusses off this beam.
-
In the meeting we also established soffit
heights, removed a little wall in the kitchen to expose the
greenhouse door, relocated the MBR closet door (centered),
adjusted several door heights. and a few more details.
-
Herb trimmed the oleander that were
getting in the way of the live cam. What a guy!

Tuesday, October 28, 2003
-
Framing the exterior of the main level. It
really goes quickly.
pictures.
-
Made an emergency trip to the site to
adjust some window locations.
-
Found out they're going to raise the lanai
level by using jacking the entire thing up and putting in
spacers. I want to see this.

Monday, October 27, 2003
-
Beginnings of the main level exterior
frame have begun. Lower level exterior framing is wrapping up.
pictures.
-
Met with Mike and Herb to discuss main
level framing details including coffered ceiling design, plant
shelf details, door heights, and the dumbwaiter shaft.
-
I think we've decided to raise the floor
in the master bath by 4" to accommodate proper slopping of the
shower floor and permit us to do this really sexy design for
the tile on the shower floor.
-
After months and months of permits and
hearings and dirt work and inspectors and tags "rouge" and
writing enormous checks, this is really getting to be
FUN! Our baby's coming together.

Sunday, October 26, 2003
-
Framing continues on the lower level.
-
The 2nd level lanai problem will be fixed
by raising the west (rectangular) portion of the lanai decking
to match the level of the trapezoidal inset section.
-
A meeting is scheduled for Monday to
discuss framing details with Mike and Herb (the framing
contractor). We've spent the weekend putting the final touches
on these details.

Thursday, October 23, 2003
-
Framing continues on the lower level.
-
Main level lanai sub-flooring has been
set, but there's a problem. The trapezoidal set-in section of
the lanai--really, an extension of the dining room--is not at
the same level as the rest of the lanai. It's about 4" higher.
This will NOT work. Mike assures me he's on top of it.
-
Provided Mike with a change drawing for a
little overhang that will extend from the east (street) side
of the greenhouse to the corner by the master bath.

Wednesday, October 22, 2003
-
Framing continues. The sub-flooring is
being installed on the main level. The tongue and groove
sheeting is being secured with about a zillion screws.
pictures
-
We can finally see what the view looks
like from there and it's really cool.
-
"Juliet" balcony has been added to the
bedroom.
-
Laurel's waiting to get the steps framed
so she can come up and see what things look like. Ladders are
not one of her favorite inventions.
-
The beam structure below the great room
lanai door is really complex. There's a photo of this in
today's pictures.

Tuesday, October 21, 2003
-
Lumber for framing the second floor was
delivered.
-
Brought in a big crane to set the glulam
beams in place and move building materials from the street
level to the building site.
Pictures. Actually, this was the second crane brought to
the site today. The first one couldn't handle the slope of the
street, so we had to get the heavy duty "ATV" model.
-
Started installing sub-flooring.
-
It's really amazing how quickly this
process is moving along. Nice to have some real action.

Monday, October 20, 2003
-
Truss and beam installation continues. A
crane will be onsite tomorrow to set the new glulams.
-
We had noted a problem with a truss being
in the middle of the dumbwaiter shaft. Now there are three
trusses in the shaft.
-
Southwest column on the lanai needs to be
rotated 45 degrees.
-
The guest BR closet wall and guest bath
door still seem to be in the wrong place.

Saturday, October 18, 2003
-
The remaining lower level beams and the
sub-flooring arrived on Friday. Framing to continue on Monday.
-
Had nice sunset
s on the lower lanai on
Friday night. Maybe by this coming Friday, we'll be on the
second floor!
-
Checked out jet tubs for the guest bath.

Thursday, October 16, 2003
-
Trusses arrived on Wednesday afternoon and
not without a little excitement. Word has it that the load
fell off the truck and completely blocked the street in front
of the house. The city came out and put up barriers, the
driver finally managed to get the load moved to the sidewalk
and the framers moved them all to the lot this morning. It
just goes to show you, it's always something...
-
Most of the trusses not requiring
connections to glulam beams were installed today [pictures].

Wednesday, October 15, 2003
-
Trusses are suppose to be delivered today
and glulam beams tomorrow. We'll see.
-
Even after all the engineering and
redesign, a couple of issues surfaced when it was time to
order beams.
-
From the two meetings I had to discuss
sunscreens, I've gotten one bid. The meetings were a week ago.
Some of these folks seem to have way too much business.

Monday, October 13, 2003
-
Still no sign of Glulams or trusses. :(
-
After a scant 4 hours on Saturday, we
managed to select the wall sconce lights for the lower level
hall; bath vanity lights for all but the powder room; fixtures
for above the bar and a
really cool sconce for the main entryway. This is going to be a
very l-
o-n-g process. I think we're already over budget.
-
Looks like someone ripped off a stack of wafer
board on Saturday.

Wednesday, October 8, 2003
-
Meeting with two sunscreen vendors today
to get bids on coverings for the west exposure of the upper
patio and the two northwest-facing windows.
-
You can't see it on the live picture, but
the porta-potty decided to relocate to the bottom of the hill
again.

Monday, October 6, 2003
-
Reworked trusses have should arrive next
Monday.
-
Redesigned beams have been ordered and
should be installed on Thursday.
-
Decided to reduce most of the first floor
doors from 8'-0" to 6'-8".
-
Interesting news from the surveyor.
Details to follow.

Friday, October 3, 2003
-
Truss re-engineering is still in the
works. Think we'll get to do more framing next week? This
process is very 'serial.' :(
-
Waiting to have the lot corners staked
(again) so the silt barrier--orange netting--can be installed.

Thursday, September 25, 2003
-
The majority of the 1st floor framing is
complete and it looks fantastic! It's reassuring to have the
real live product mesh with what we imagined while drawing
plans.
Wrap up pix.
-
Ran into some span/size problems while
engineering the floor trusses. Story is that when the truss
companies bid jobs, they basically guess. The actual design
revealed some spans that were just too big, so we're
re-engineering. This process requires redoing the
architectural drawings, engineering analysis and COP review.
The new design may also require new load bearing points and
therefore entail cutting the floor and pouring new footings.
This should all be wrapped up early next week. I guess it's
not how big your truss is, but what you do with it. Bummer,
dude.
-
Met with COP building inspectors to
discuss debris issues.
-
Enjoyed a sunset, the evening view and an
adult beverage on the lower lanai.
Pictures.

Wednesday, September 24, 2003
-
Framing day three and things are moving
right along. The exterior walls in the garage, laundry, and
rear of the house were erected this morning (before it was
light enough to capture the activity on the web camera)
Framing
days 2 and 3.
-
The framing is really looking
nice--quality work.
-
Thanks to Herb for a little "ride" on the
forklift to allow me to adjust the camera position. Request
for hazardous duty pay has been made.
-
Engineering drawings for the greenhouse
have been ordered.

Tuesday, September 23, 2003
-
Framing is moving right along. Most of the
outside walls are complete and should be raised tomorrow.
-
Met with our framer, Herb, on site to
discuss minor plan changes.

Monday, September 22, 2003
-
Framers, albeit a half crew, showed up and
started framing. They're hauling the lumber down from the
sidewalk a stick at a time.
Framing
pictures
-
The framers drove down to the lot and had
quite a time getting back out. See the
POD.
-
City of Phoenix showed up to install the
water tap. I guess the main makes a 90 turn right in front of
the house and they had to get a supervisor out to decide what
to do. Nothing's easy with this project.
Water
pictures

Sunday, September 21, 2003
Friday, September 19, 2003
-
Work stopped in observance of
International Talk Like a Pirate Day. Arrrrr! It makes me
shiver to think me timbers are laying in a pile and not going
up. Abandon all hope, ye who plan to build a house.
-
ITLPD Resources:
ITLPD website (may be overloaded)
Pirate Gear
Dave Barry Article

Thursday, September 18, 2003
-
Lumber arrived today. They moved a few of
the glue-lam beams down on the lot, but the rest is in three
stacks on the sidewalk. There's also an enormous glue-lam beam
on the adjoining lot.
-
Current story is that the framers will
arrive on Monday.

Tuesday, September 16, 2003
Monday, September 15, 2003
Saturday, September 13, 2003
-
Framer is finishing another job. He's
suppose to be finished by Monday, Tuesday at the latest.
-
Still playing in the dirt at the bottom of
the slope.
-
On a related topic, while playing in the
dirt to remove the barriers, it looks like the sewer
connection suffered a little "scoop rash."
-
We'll probably be redesigning the roof
drainage system. Goal is to remove the west-facing scuppers;
direct the runoff east and down piping on the west side.

Friday, September 12, 2003
-
No lumber today.

Wednesday, September 10, 2003
-
Crane arrived and barriers have been
removed. Whole boatload of pictures
here.
-
No sign of the City of Phoenix and the
scheduled water meter installation.
-
Want to make book on when we'll see
lumber?

Tuesday, September 9, 2003
-
Work on the dirt at the bottom of the
slope continues.
-
Spoke with Under Glass Manufacturing today
to reconfirm initial specs for the greenhouse. This one I'm
really excited about!
-
Water meter is scheduled to be installed
on Wednesday. Also, the crane is suppose to be here to
lift out the barriers.

Monday, September 8, 2003
-
Working on the dirt at the bottom of the
slope to prepare for the removal of the temporary barriers.
All this activity is out of camera view. Still pictures are
here.
-
The mini-track hoe was driven across the
slab. Very glad it has a rubber track!

Friday, September 5, 2003
-
On Wednesday the Bobcat showed up; today
it left. Must have been suffering from extreme boredom.
-
Another week has passed and other than a
little lookin' and scratchin' on what it'll take to remove
some construction barriers, there's been NO forward
motion. If you click
here, you'll see something that's moving almost as
fast as this project.

Wednesday, September 3, 2003
-
The Bobcat got delivered today. Stated
reason for not starting on Tuesday and working today was that
the access path we were going to use to get rid of the excess
dirt was blocked. Dirt work is now scheduled for tomorrow with
lumber delivered on Friday.
-
Our new web server's up and running. The
change should be transparent to everyone. This new server will
help us keep the status more up-to-date, make blog maintenance
easier and allow us to do a bunch of other cool stuff.
-
Added a "days since groundbreaking"
counter to the status frame.
-
Looking at our web logs, we've just seen
visitors from Poland and Japan.

Monday, September 1, 2003 - Labor Day
Friday, August 29, 2003
-
The saw cutting of the well-cured concrete
is complete (550 ft.). It looks quite nice. They concrete
cutting company ended up using a small, hand-guided saw for
the job because the couldn't get their large, self-propelled
unit down the steep drive.
-
The inspiration for the concrete floor
with saw cuts came from Flo's Asian Restaurant in Scottsdale.
Turns out the guy who did our cuts did Flo's too! Pretty cool.

-
Still no dirt work.

Wednesday, August 27, 2003
Monday, August 25, 2003
Saturday, August 23, 2003
-
Not a lot happening with the dirt, but we
did make a few interior design decisions (among the first) for
the master bath floor. For the floor of
the shower, we've picked a mosaic that is made from actual
river rock. The pattern we selected has a soft green cast. For
the bath flooring we've chosen a tile that almost matches the
rock and for the walls of the shower we're using a similar
tile in a putty color.
See the pictures
-
Laurel came up with a
design for the interior shower wall that raises it above the
rock tile. This allows us to carry the shower tile out into
the main room for about 6". Very cool.
-
Tropical storm
Ignacio is coming ashore over the Gulf of California.
Hopefully, the remnants won't bring too much rain to Arizona
(but we can use the rain).

Friday, August 22, 2003
-
The marking for framing and saw cutting is
complete. Saw cutting is scheduled for Monday.
-
Reason for all the cross-hatch lines in
the slab is that we're leaving the concrete exposed in the
media room, hall and office. The concrete will be treated with
an acid stain and coated with an epoxy finish. The saw cut
lines just add a little decorative pattern.
-
Remedial patching of the concrete in the
media room is scheduled for today.
-
The lumber package is on the way.
-
Dirt work cleanup is
scheduled for Monday.

Wednesday, August 20, 2003
Tuesday, August 19, 2003
-
Not much happening.
-
Behind the scenes were looking at stains
and coatings for the lower level floor and trying to find
someone to sell us stairs. Out of 4 requests for call-backs,
I've received 1. Been working on this since September of 2002.
-
Added Rick Carter's party pictures to the
site.
View

Friday, August 15, 2003
-
Celebrated the completion of the
foundation and slab.
See the pictures.
-
A little remedial dirt work is up next
along with some concrete touch-up.
-
Prior to the start of framing we'll be
making saw cuts in the concrete floor in the media room, hall
and office. We're leaving the concrete exposed and will be
treating it with stains and coatings.

Thursday, August 14, 2003
-
The slab is done and it looks great.
Pictures will be up soon. Hard to believe, but it took Over 40 cubic yards of concrete to complete the footings, stem
walls and slab.
-
Had our second monsoon storm last night.
This one was a biggie.
-
A couple of weeks ago, we made a small
design change in the lower level lanai. We added planting
areas around the columns and at next to the wall. Control
joints connect the front and rear planting openings. They're
aligned to match the angle of the media room door. They look
great!

Wednesday, August 13, 2003
-
Pouring of main floor was completed. It
took 3 truckloads of cement to complete the job. With
the pour starting at 11:00 AM (extremely late by Phoenix
standards) the 109° heat made it
hard for the workers and the cement really set up quickly.
-
Poured the radius
corner stem walls in the garage.

Tuesday, August 12, 2003
Monday, August 11, 2003
-
Copper plumbing passed inspection. The
fine grading will be completed tomorrow, along with the forms
for the patio. Pouring is set for Wednesday and Thursday.
-
Having problems with the phone line for
the web cam. It's quite intermittent. Qwest is sending the
cable team out tomorrow, to try and locate a ground leak.
-
Blue stake folks from Southwest Gas and
APS were out to do the mark things so the city can dig for our
water connection.
-
It's hotter than hell out here!

Friday, August 8, 2003
Thursday, August 7, 2003
-
The copper was red-tagged. City of Phoenix
code requires that all copper be wrapped, which it is. Seems
that we have a requirement for all runs through a bearing
footing also be sheathed in ABS pipe. Both our plumber and our
contractor have over 20 years in the business and for both of
them this is a first. Live and learn.
-
The plumbers are making the changes today,
so we should be up for a re-inspection tomorrow.

Wednesday, August 6, 2003
-
Copper plumbing is complete and ready for
inspection. With a hot water circulation system (eliminates
the delay in availability of hot water at the tap) and the
soft water loop, there's copper everywhere.
-
Forms for the radius corners in the
garage, the areas of the main floor, the outside of the lanai
(patio) and one column footing on the south side are set and
ready to go. We added some artistic detail to the floor of the
lanai and that needs to be formed.
See the work in progress.

Tuesday, August 5, 2003
-
Grading for the slab is complete. On the
live picture, you may be able to see the difference in height
between the main floor and the garage floor and even the slope
of the garage floor (about 3" front to back). This is pretty
exacting work, considering it's being done in dirt.
-
Now that the base for the slab is all
smooth--the work of people we call "the puter-iners",--it's
time for the plumbers to come and dig for the copper plumbing
and to expose the bearing wall footings. These are "the
taker-outers." If the puter-iners can get significantly ahead
of the taker-outers, then the house is complete.
-
Door opening in the stem wall for the #2
bath is being relocated a little south.

Monday, August 4, 2003
Friday, August 1, 2003
-
First floor plumbing has been covered and
work was begun on grading to establish the slab level.
Unfortunately, the tractor broke down. We've broken a lot of
hardware on this project.
-
AB Gravel was delivered late Friday. This
will be graded to form the base for pouring the slab.

Prior Journals |