|
Aloha Friday, December 23, 2005
Monday, December 12, 2005
-
Back from the land of Aloha and we've
got lots to do. My NT950 cable certifier is here, but I
still need to finish termination on the MDF ends of the coax
cables.
-
In between bouts of Xmas decorating, I'm
also trying to do a little Concerto central audio system
installation.
-
The repainted house front looks MUCH
better.
-
Camera uploads have been a little
intermittent for the last couple of weeks. Problem was on my
web host's end. Their FTP sever is running very slowly
causing upload sessions to time out. FTP has been
moved to the Hale Nani website server. Things seem OK.

Monday, December 5, 2005
-
Nothing going on at Hale Nani. I'm
spending a few days in Kihei working, albeit at a generally
leisurely pace, on the condo (Hale Nani Lite).
-
While I was gone, my cable
certifier hardware arrived. Should be interesting to see how
all those miles of CAT5 survived the construction process,
not to mention my installation techniques.
-
Time to head for town--again--and score
more parts. No, Laurel, this trip doesn't involve a stop at
Henry's ;-). A hui hou.

Monday, November 28, 2005
-
Way back in the early summer when, as a
part of the leak repair issue, the stucco was repaired on
the front of the house. Following the repair, the paint was
touched up, but the color matching was not even close. Today
the painter is re-spraying the entire front of the house.
BIG job
Monday, November 21, 2005
-
On Wednesday, the 16th, I finished
terminating all the CAT5 cabling. Most of the data and phone
equipment is in the rack.
Pictures. Coax termination is up
next and then it's time to get the central audio system
installed.
-
Since we have all this new cabling up
and running, I've put the #2 cam back online. Yes. I could
have done it wireless, but where's the challenge in that.
Today we're in the greenhouse.

Monday, November 14, 2005
-
Live camera was down while I was moving
cables and terminating telephone wiring. Punch-down of the
lower level telephone wiring is complete. Hopefully, I can
get the rest of that segment done tonight.
-
On Friday, I ordered a
Nuvo Concerto 8 zone, 6 source whole-house audio
amplifier. 40 watts per zone, programmable display panels,
controllable via a serial port, etc. It'll be delivered
tomorrow. Glad it's coming, but it's one more item on the
do list--and this one's a big sucker.
-
Word from the contractor is that the
painter should be here a week from tomorrow to re-spray the
front of the house. He was last here in July and said he'd
be back as soon as things dried out (it was raining). I
didn't realize it was that wet.

Wednesday, November 9, 2005
-
The 19" equipment rack in the MDF is
bolted to the floor and cables are being routed from the entry
points in the ceiling to the rack.
-
I'm working on replacing Qwest lines with
a VOIP (Sun Rocket) phone system. For the non-techies, this
runs phone calls over the internet via our broadband service.
The only sticking point is the fax machines. They aren't
terribly reliable a VOIP line. I'll probably have to replace
that functionality with a web-based fax service.
-
Contractor is back on the job addressing
a little grading issue.

Wednesday, November 2, 2005
-
Audio CAT5 is terminated. Whew! A lot of
punching-
pictures. Next the rack gets bolted to the floor and we
start terminating phone lines.
-
2nd Halloween at Hale Nani attracted
about 25 little gremlins.
Pictures.
Monday, October 31, 2005
-
MDF wire termination continues. Line
level audio (stuff connected to speakers) is all terminated.
Through very bleary eyes, I wrapped up the audio CAT5 on
Sunday. Bolting the rack to the floor is on the schedule
today, but with work and timeout for pumpkin carving, I'm not
sure it'll get done. We're thinking about adding a water
softener/filter. That equipment goes in the MDF, behind the
rack and it's getting a little tight in there. Next house, the
hi-tech equipment gets its own room.

Thursday, October 27, 2005
-
OK, so maybe not quite done. I just got
tired of rehashing the same old crap and slicing off hydra
heads. Plus, I didn't realize there were still people actually
reading this drivel.
-
MDF (Main Distribution Frame, aka. da
place where all the wires go) termination continues. Line
level audio (stuff connected to speakers) is all terminated.
Audio CAT5 pairs should be finished tomorrow. Then it's on to
the data, phone and video cables. Several of the drops have
been in use on a "temporary" basis, so I'm having to manage
what I'm tearing up while I do the final installation, less we
be left without phones, Internet connections, etc.
-
Original plans called for a hole in the
floor of the #2 BR closet to be used for an in-floor safe. The
concrete guy never framed it and a follow-up saw cut never
happened. As a substitute, I bolted a cheep ol' fire safe to
the floor of MDF. Not quite like the in-floor option, but then
we don't have a lot of stuff that needs Ft. Knox West.

Thursday, October 20, 2005
The End.
Monday, October 17, 2005
-
One of those little things we missed
during the design phase was the lack of a top row of drawers
in the master bath vanity. Of course, the panels in front of
the sinks are fixed, but this was also true of the panels on
either side of the sink. When we first noticed this, shortly
after install, RC Cabinets told us there was room for
drawers because of the width of the sinks. Not true. I
called RC to see if I could order drawer boxes. They gave me
a verbal quote of $40.00 a piece, but when I got the faxed
bid, they'd gone up to $60.00. A little Googling lead me to
a shop in California that specializes in drawer boxes. The
entire order was entered through the web and 5 days later
the UPS dude delivered 4 maple, dove tailed, pre-finished,
bull-nosed edge drawer boxes with full extension glides.
All this for under $45.00 a shot. I spent Saturday
installing them and now when you pull on one of those upper
panels (even after a year, it was surprising how many times
I tried that) a drawer is extended. One more item off the
"Honey-do" list.
-
Rooter guy managed to dislodge whatever
it was that was plugging up the the #3 shower drain. Sure am
glad we didn't have to chop any concrete to get that problem
fixed.
-
Structured wiring parts are finally
here. Punch-down work should be completed this week.

Tuesday, October 11, 2005
-
As most visitors to this website are well
aware, we've had our share of challenges with the Hale Nani
project. In some cases, a problem's source was easy to
identify. In other areas, I've had a hard time putting my
finger on the gremlin. That is, until today. A review of the
library has uncovered this photo of
a laborer. Enough said.
-
At long last, I'm wrapping up the
labeling of the structured wiring terminations. NOC parts
are on order and the completion of that end, save for the
audio/visual hardware, should be completed next weekend.

Monday, October 3, 2005
-
It took a long time, but the greenhouse
is done and it's a fantastic addition to the property. The
final glass segments went in without a hitch and rather than
building plant tables, I bought and modified three Home
Depot 24 x 36 shelving sections. They're ideal for the job.
Pictures... I still have to do a bit of wiring for the
rope lights. At present, they're running on extension cords.
Also, I need to mount cleats on the parapet to anchor the
ropes for the sun shades (at present, they're lashed to the
swamp cooler), but both jobs are small potatoes. Bring on
the seedlings!

Wednesday, September 28, 2005
-
Rope lights are up in the greenhouse.
-
Still waiting for our final glass panel.
It should be here soon.
-
Primed the doors on the roof deck sink.
One of these cool mornings (it's still only going down to
about 80 at night), I'll get them painted.

Sunday, September 25, 2005
-
A new piece of greenhouse glass is
being cut from the pattern I made. Should be here by
Wednesday.
-
Installing rope lights in the
greenhouse. I looked at a number of ways to attach the light
clips to the aluminum ribs. These included drilling holes in
the ribs and using tie wraps, or cutting, drilling and
tapping about 120 1/8" x 3/4" aluminum "nuts" that would fit
in the channel in the rib (best method, but way too time
consuming). Finally settled on cutting 1/8" steel rods into
1/2" sections, slipping these into the aluminum channel and
tie wrapping the mounting clip to the rod. It's a little
Rube Goldberg, but I think it'll work fine.
-
Garret the tile guy replaced the grout
in the foyer. Looks much better. He also returned the rented
scaffolding I used for GH glazing. Thanks much Garret!!!

Thursday, September 22, 2005
-
On the greenhouse, grinding proved not
to be an option. I created a template out of 1/8" foam core
and I'll order a new window.
-
One of the lower panels on the standard
part of the greenhouse was installed improperly (last
November). It rested on the stucco ledge, as opposed to the
lower end of the greenhouse frame. There was also a little
piece of wooden shim wedged in between the glass and the
frame. The plan was to loosen the cap strips and slide the
window up into the proper location, but when I tried to do
this, the window wouldn't budge. Turns out it had been
basically been stuccoed and painted in place. After
fifteen minutes of chipping and grinding, I got the glass
freed up and moved to it proper spot.

Wednesday, September 21, 2005
-
This greenhouse saga never ends. As you
can see on the camera, the scaffolding got moved. With the
light of dawn at my back, I tried installing the new small
"pie" in the east gable, but no fitty. At
about the 2 o'clock postion the
arc is a bit wide and that's preventing it from fitting
fully up into the channel. Plan is to go buy some grinding
discs and see if I can shave a couple of 16th off of it.
Tuesday, September 20, 2005
-
Survived another TLAPD. Argh!
-
On Monday, I spent two hours on the
phone trying to find someone to install the rest of the
greenhouse glass. I had NO success. Most glaziers just
didn't want to do the job; many said they too busy. One guy
said he'd do it, but it'd be a four-man crew and no
guarantees if the broke stuff or couldn't finish the job. It
was all very frustrating, but I finally decided to move this
effort back to the DIY list. Using wooden shims, aluminum
flashing and a bunch of duct tape I fashioned a ramp to help
guide the glass into the frame. To make the work surface a
bit more stable and to give me a better angle from which to
handle the glass, I moved the scaffold platform two notches
lower--much better. At the crack of dawn today, Laurel and I
tackled the task. Vertically, the opening is about 1/8"
smaller on the south end than on the north and the glass was
a bit oversized, so I couldn't use the "H" gasket that is
suppose to go between the upper and lower pane, but that's
why Dupont invented silicone. Anyway, all the glass is
installed in the west gable. I've got to move the
scaffolding tonight and tomorrow I'll finish the upper "pie"
piece in the east gable and fix one of the lights that
wasn't installed quite right when Hans was out. One of these
days this task has to be in the pau column.

Monday, September 19, 2005
-
Avast, me hearties! It's International
Talk Like a Pirate day.
-
Getting the largest glass (light) in the
west gable of the greenhouse proved to be problematic.
There's just no way that I can get a good grip on it.
Calling in the glaziers today. I want this damn greenhouse
done.
-
Just wrapped up cleaning the stair
rails. One more job off the do list and if you don't look
too closely, it's a pretty good job.
-
Replaced/repaired the guide cables on
the south-most sun shade. This job turned out to be a little
easier than I thought. This is good, because I suspect this
won't be the last repair. Those 9' x 11' shades make VERY
good sails.

Aloha Friday, September 16, 2005
-
The replacement glass for the greenhouse
was delivered yesterday. Out of fear of breaking, I have
tried it out to see if it fits. Installation, along with
glass cleaning and touch-up painting is on the lists for
tomorrow. I sure hope we've got all the greenhouse gremlins
under control.
-
The demo string of rope lights in the GH
looks way cool! Installing 5 more is also on the schedule
for this weekend.

Monday, September 12, 2005
-
The three replacement tempered glass
panels for the greenhouse have been measured and ordered.
The glass company wouldn't deal with me directly, so I had
to send all of the information to the GH manufacturer in New
York and they placed the order. Under Glass Mfg. has been
really good about working out the problems with this little
structure.
-
Painting of the stair structure is
finally COMPLETE. That thing has really been a pain. Today
I'll clean the glass--not a simple task--and then I don't
want to see that structure for a few weeks.
-
Today I'm installing a string of rope
light on one of the ribs in the greenhouse. If it looks OK,
we'll do the other 5 ribs.
-
Installed a work surface light in the
greenhouse.
-
MJR (contractor) sent a rep out look at
the etching on the aluminum window frames. He concluded it
wasn't a water stain. Stucco guy says it's not his problem
and now the contractor says there is nothing they can do
about it. This one will stay on the open item list. "Mikey,
you're doing a heck of a job."

Sunday, September 4, 2005
-
Today's attempt to install the
greenhouse glass was far less fruitful than I'd hoped. Of
the 8 panels that Hans the installer (from last
November) had templated, three didn't fit. Curved piece at
the top of the east gable is about an inch too long and the
two center sections on the west gable are too narrow. Except
for the lower east panel, the other fittings were also less
than marvelous, but with a little came tweaking, we got them
in. This is tempered glass, so it'll all have to be re-cut.
Bummer! I was hoping to spend Labor Day tending to a new
crop of rare herbs and spices. [Pictures]
-
On the plus side, I did get the gap at
the top of the west gable (a result of an install
measurement error) patched and sealed in a reasonable
manner. A little aluminum flashing, sheet metal screws and
some caulk did the trick.

Saturday, September 3, 2005
-
Got the scaffolding on the west end of
the greenhouse erected this morning. It's a little scary up
there, but it's still the best, and I think only way to work
on that side of the structure.
-
Caulked the exterior of the west end of
the greenhouse and measured, cut and installed the
rubber came (a plastic version of the stuff used in stained
glass work) on the glass panels that'll be installed
tomorrow.

Friday, September 2, 2005
-
About 4:30 yesterday afternoon, a late
season monsoon dust storm snuck in and a huge blast of wind
popped the guide cables on the southern-most sunshade loose.
Oops.
-
At long last, stair trim is painted. A
little touch up here and there, but if you don't look too
closely, it seems OK. I should have insisted on having the
mounting parts for painting prior to assembly.
-
Today I picked up 5- and 7-foot sections
of scaffolding to be used for this weekend's glazing of the
greenhouse. Not exactly sure how it'll be erected, but as my
mother can attest, as a child I was the king of the Erector
Set. Filling up the rental truck used to schlep the
scaffolding cost me $3.25 a gallon. Last time I paid that
much for petroleum distillates, the pain, vin blanc and
fromage were MUCH better.
-
Stucco guys were here yesterday to
inspect the etching of the window frames and per spec, their
response was "no mi problema." This'll be pursued through
the contractor. I'm sure that'll be effective.
-
Louisiana, Mississippi and Alabama have
been devastated, but it's comforting to know that the
various spin machines are going to allow the Platitude
Purveyor in Chief to escape unscathed.

Monday, August 29, 2005
-
I thought I had an access plan finalized
for glazing the west end of the greenhouse, but upon further
review I decided a bit more study was needed. It's tight
quarters and it's a long ways up, or down, depending on your
view. I've considered framing a stand. That's a lot of work
and I'd worry about stability. Plan now is for two six foot
scaffolds. One will be at the base of the stairs and will
support planks that intersect the stairway at the 6 foot
level. The second scaffold will be built on top of the plank
bridge. It'll be a little low, but that's why they built
step ladders. I just want this damn thing done.
-
Masking the staircase trim parts took
over three days. Subsequent primer panting took about 20
minutes. Final coat(s) go on today and then this baby's pau!

Monday, August 22, 2005
-
Yes! I know, I've been doing a really
crappy job of updating the journal, but it's the Dog Days of
Summer, Laurel and I have been doing a bit of traveling and
there just hasn't been much progress.
-
The painter showed up a couple of weeks
ago to address the painting problems on the front of the
house--the patched areas don't match the un-patched areas.
Good news is that he volunteered to re-spray the entire
front. Bad news is that it was too rainy and we're on the
schedule for "when things dry out." I hate those
indefinite dates.
-
Finally made a small amount of progress
on the greenhouse glazing. On Sunday morning, I climbed [POD]
through the east gable opening and and caulked the interior
and exterior of the frame. The interior of the west end is
on the schedule for tomorrow. I've got a couple of plans for
how I'm going to work on the exterior. but 20 feet off
the ground, it's a tough spot to get to. This is
particularly true if one is a chicken and fears dropping to
the cement slab below. Would make for an interesting web cam
picture, though.
-
The drain in the office shower is very
slow. The thing's been used no more than 50 times since we
moved in, so I'm assuming it's a systemic blockage of some
kind--perhaps a handful of roofing nails. I shoved a snake
down it and found a pretty firm blockage about 4 feet down.
I suspect that getting the builder/plumber to do something
about it's going to be a challenge.
-
Added a dimmer to the dining room light
and split the kitchen LV over-counter can lights to two
switches--one for the island and one for the counters

Monday, August 8, 2005
-
We're in the middle of monsoon season,
and this year the storms have been pretty active. On
Tuesday, August 2nd, we had two hours of the hardest rain
I've seen in the 18 years I've lived in Phoenix. About 300
yards up the block, an enormous wash developed, littering
the street with 10 lb. rocks and tons of soil. Dozens of
homes in our neighborhood were flooded. The point of this
little weather report is that the 10-month battle with leaky
roofs and walls has now been verified to have ended in
success. One of the 19 foot windows in the stair tower
leaked a bit, but considering that the torrential rain was
being driven by 40+ mph. winds, I'm not too concerned.

Monday, August 1, 2005
-
I have a little remedial landscape and
concrete work that needs to be done, but trying to find a
contractor in this town (or any other, from what I've heard)
who'll call you back is close to impossible. I'm spending
more time one the phone, tracking down someone to do the
work, than the jobs will take.
-
It's hard to believe we've been in the
house for a full year! Dismayingly, the DO List doesn't seem
much smaller.
-
Our xeriscape plants are showing the
strains of the second hottest July on record.

Monday, July 25, 2005
-
Oops! Web cam had been down since late
Saturday night. I think a PM storm tripped the GFI in the #3
bath.
-
A big part of building a house with
something other than an open-ended budget is compromising on
selected elements. Our front staircase is a prime example of
this. The end product is wonderful, but we definitely shaved
a few corners here. The caps that hold the glass railings in
place were not available when we painted the steel. They
were attached "raw" and now I have to go back and mask and
paint them. The painting is pretty easy, a coat of prime and
a couple of coats of paint, but the masking is a different
story. There are 66 units to be masked and it's taking me
about 20 minutes per unit. Two of the locations require
makeshift scaffolding. Another one of those "bigger than I
had imagined jobs."
-
The drain in the #3 shower is plugged.
Given that we've used it no more than 50 times, I think we
may have a systemic problem.
-
Adjusted the sweep strip on the Juliet
balcony door. Prior to the adjustment, medium-sized rodents
could stroll in pretty much unimpeded.
-
With all the animal references, I've had
been questioned about my relationship with Marlin Perkins.
To show my diversity, this week's oddity involves flora, not
fauna. See the
photo album.

Monday, July 18, 2005
-
This has nothing to do with Hale Nani
other than we do need a good laugh around here from time to
time. Best quote of the week:
"For Bush to get rid of Rove would be like Charlie
McCarthy firing Edgar Bergen."--Marshall Wittman
-
Painting over the wall patching I did
when I installed the bar counter lights and also finishing
up the paint on the stair hardware brackets that hold the
glass rails in place. We painted the rest of the stair
structure before the glass was installed.

Wednesday, July 13, 2005
-
Not much happening on the construction
scene, but I do have an update on the fauna front. Now that
we're in the 110° plus days, Zoë's et
al have been getting the daily walk in at around 5:00 am. On
Monday, Zoë was showing particular interest in one of our
neighbor's bougainvillea bushes. When I went to see what was
enticing her sniffer, I found myself face to face with a
raccoon. The coon was well off the ground and the dog never
did see it, but it certainly got my attention. We picked up
the pace and headed on down the road.
-
I'm getting close
to ordering the central audio hardware. Gotta get that rack
bolted down first, though.

Thursday, July 7, 2005
-
When we built the master bath, we had to raise the floor to
accommodate the shower without a surrounding curb. This was done
with a 2x4 platform in the tiled area. This morning while Laurel
was showering, she saw a small scorpion just outside of the
closet door. Before she could squash the little bugger, it
disappeared into a minute crack in the grout next to the south
wall. I suspect we've got creepy-crawlies living under the
master bath raised floor. Good thing the bug lady's coming
today. Once she leaves, I'm getting out my trusty silicon
caulking gun and seal up the any pukas (holes) I can find.
-
Early morning yard work is being ignored while we follow the
Tour de France action. Il est magnifique!

Wednesday, July 6, 2005
-
The 2nd annual Hale Nani Fireworks Extravaganza was great fun!
Save for a little paint, I got the roof deck sink base
resurrected in time for the party. It's great to have our upper
deck fully operational again.
-
What's not nice is the return of our arachnid visitors. On July
4th, while giving a little house tour, Laurel found a scorpion
in the Master WC and last night, Zoë found one at the main floor
stair landing. Bug ladies will be here tomorrow.
-
Finally got our chuckwalla pictures. Here they are:

|
|

Mr. Chuck and a lady friend
|
Prior Journals |